How to write an out of scope email to a client.
An out of scope email that keeps the client happy. Say yes to them, offer a price, a swap or a later date, and get their OK first.
On this page
Why it’s awkwardCheck what you agreedReply with a yesWhat to sayGet their OK firstStop it next timeLet it run itselfThe short version
Why one small extra is hard to say no to.
A client asks for one more page or another round of changes. It’s not in the proposal, but saying so feels petty. A good out of scope email lets you raise it without any awkwardness.
Most owners just do the work instead, and next month it happens again. The email isn’t a no. It shows the client their options and lets them choose.
Check what you agreed.
Reply with a yes and some options.
Confirm it in writing.
Bill the extra as agreed.
Add one line about extras.
Check what you agreed.
Open your proposal or agreement and look for the request. If it’s clearly not there, it’s out of scope. If the wording is vague, it’s fair to talk it through with the client rather than send a price straight away.
If you’ve already done a small extra for free, that’s fine. Just mention it, so the client knows it was a favour and not part of the plan.
Your proposal or agreement is what sets the scope. If the amount is large or you can’t agree, get advice for your situation.
Reply the same day, with a yes.
Don’t ignore the request and don’t quietly do it either. Both make the next conversation harder.
Start with what you’re happy to do. Then say it sits outside what you agreed. Keep it friendly and matter of fact, because it’s normal for projects to grow.
What to say in an out of scope email.
A choice feels much better than a no. Most out of scope requests fit one of these.
- Add it for a set price, on top of the current work.
- Swap it for something in the plan that matters less to them.
- Park it for a second stage once the current work is done.
Hi Kate,
Happy to add a separate menu page. It wasn’t part of the original plan, so here are a few ways we could do it.
We can add it for $480 and it will go live with the rest of the site. We could also swap it for the blog page if that matters less right now, or leave it for a second stage in March.
Let me know which suits you best.
Thanks, Sam
Get their OK before you start.
Once they choose, confirm it in one short email before you do any of the work. That way the price and the timing are written down and nobody is surprised later.
Then add it to your next invoice as its own line, so it’s easy to see what it’s for.
Hi Kate,
Thanks for confirming. We’ll add the menu page for $480 and it will go live with the rest of the site on 4 December. I’ll add it to the next invoice.
Thanks, Sam
Stop it happening next time.
On a retainer, small extras tend to creep in a little each month. Keep a simple list of them. If the same extra keeps coming up, raise it at your next check-in. Then price it into the retainer from the next month, so you’re not having the same chat every few weeks.
In every new proposal, add one line that says how extras work. You can copy this one.
Anything not listed in this proposal will be quoted separately, and we’ll get your OK before we start.
Let it run itself.
The hard part isn’t writing the email. It’s doing it every time, and making sure the extra ends up on the invoice.
IniDeck can handle the follow-through.
It drafts the out of scope email, adds the agreed extra to the next invoice and waits for your OK.
Keep reading
Related guides.
How to follow up on a proposal without being pushy
How to follow up on a proposal that’s gone quiet. Check in after three working days, ask one easy question, call, then close the loop.
How to chase a late invoice without losing the client
A polite, step-by-step sequence that gets you paid and keeps the relationship.
Christmas shutdown checklist for small businesses
A Christmas shutdown checklist for service businesses. What to do four weeks out, two weeks out, on your last day and your first day back.
Keep reading
Related guides.
How to follow up on a proposal without being pushy
How to follow up on a proposal that’s gone quiet. Check in after three working days, ask one easy question, call, then close the loop.
How to chase a late invoice without losing the client
A polite, step-by-step sequence that gets you paid and keeps the relationship.
Christmas shutdown checklist for small businesses
A Christmas shutdown checklist for service businesses. What to do four weeks out, two weeks out, on your last day and your first day back.